7月30日,蘭石重裝儲能公司承建的國家能源集團敦煌“光熱+”100MW熔鹽線性菲涅爾光熱項目,2臺高低溫熔鹽儲罐主體安裝完工,順利進入設備接管裝配、盛(sheng)水試(shi)驗、保溫(wen)防腐等(deng)工序(xu)。
自5月中旬高低溫熔鹽罐(guan)基礎(chu)土建(jian)工(gong)(gong)(gong)程(cheng)完工(gong)(gong)(gong),進(jin)(jin)行設備安裝工(gong)(gong)(gong)程(cheng)以來,蘭石重(zhong)裝項(xiang)目團(tuan)隊精(jing)心組織、科學施工(gong)(gong)(gong),克服高溫、大(da)風天氣等不利因素影響,充分(fen)發揮(hui)項(xiang)目管(guan)理和專(zhuan)業技(ji)術(shu)優勢,強化罐(guan)體拼裝、焊(han)接工(gong)(gong)(gong)序銜(xian)接,有效保證了焊(han)接質量和施工(gong)(gong)(gong)進(jin)(jin)度,實現了直徑33.8米、高15米的大(da)型罐(guan)體結構件毫米級(ji)的高精(jing)度對接,為項(xiang)目總體進(jin)(jin)度目標(biao)的實現奠(dian)定了堅實基礎(chu)。
該(gai)項(xiang)(xiang)目熔鹽(yan)儲罐(guan)主體安裝的(de)圓滿(man)完工(gong),標志(zhi)著項(xiang)(xiang)目建(jian)設取(qu)得重大(da)階段(duan)性進展。蘭石重裝項(xiang)(xiang)目團隊和參建(jian)單位表示,將(jiang)以此為(wei)契機(ji),繼續嚴(yan)把每個環節、嚴(yan)控每個細節,全力以赴保證后(hou)續工(gong)程按節點有序推進,為(wei)客戶提供(gong)高品質的(de)施(shi)工(gong)交付服務。